Glostrup Varme A/S – Establishment of transmission line to Glostrup Hospital

Glostrup Varme has entered into an agreement with Glostrup Hospital regarding the supply of heat based on sustainable district heating.

In relation to this, a new transmission line from VEKS’ heat exchanger station at the hospital to the hospital’s existing heating installation is going to be established.

Damgaard is responsible for the detailed design of the transmission line. Furthermore, Damgaard is participating in the coordination with the hospital, to ensure that the initialisation of the transmission line is on time with minimum inconvenience.

As part of the detailed design, a 3D model of the heat exchanger unit has been made, along with the detailed design of piping and components, static calculations, etc. Furthermore, Damgaard is responsible for construction management and supervision during the construction phase