Guldborgsund Varme A/S (Brøndum) – Installation of new transmission lines

Guldborgsund Varme A/S has produced a pilot project regarding the establishment of a new district-heating connection under a railway area. The connection will replace the existing district-heating connection across the bridge that was removed in the winter of 2014/2015, in connection with electrification of the railway line between Ringsted and Rødbyhavn.

Damgaard is consultant for Brøndum in a turnkey contract. The district heating system consists of two Ø323 district heating lines and two Ø40 conduits.

The district heating lines are led from Højbrogade through a booster station, across a car park to Brovejen, under the railway area to the grounds of the sugar factory and continue on through Østerbrogade.

The consultancy work was extended to also include consultancy in connection with obtaining the level crossing permit.